Watch: Drone footage shows incredible images of Manawatū to Tararua highway

Share

A new video showing the progress of the work along the 12-kilometre $620 million highway connecting Manawatū and Tararua has just been released.

The drone footage, released by Waka Kotahi NZ Transport Agency, takes viewers from the western access at the Ashhurst end of the Manawatū Gorge to the Woodville plains.

The highway, called Te Ahu a Turanga, includes the construction of six bridges and works involving six million cubic metres of earth.

Waka Kotahi’s video comes with a commentary by project engineer Chrissy Reid who described some of the challenges.

Waka Kotahi has released their latest flyover video of the Te Ahu a Turanga Manawatū Tararua Highway. Work is progressing well across the length of the 12km project.

Waka Kotahi

Waka Kotahi has released their latest flyover video of the Te Ahu a Turanga Manawatū Tararua Highway. Work is progressing well across the length of the 12km project.

READ MORE:
* Shared pathway improvements proposed for Ashhurst
* Moa bones found during Manawatū highway build date back at least 180,000 years
* New gorge highway project alliance wins diversity award

For example, she spoke about the challenges of the wet conditions in Zone Three at the top of the hilly range.

“It’s in a gully at the top of a hill, and it’s really wet, so we’ve spent a lot of time this winter getting some culverts in there and a few stream diversions just to set us up to try to get some great progress done in the summer months.”

Cut 28 which is the deepest cutting in alignment 61 metres from top to the sub grade of the road

Waka Kotahi

Cut 28 which is the deepest cutting in alignment 61 metres from top to the sub grade of the road

Reid talks about features such as Cut 28 which was the deepest cutting in alignment 61m from the top to the sub grade of the road.

“There some really cool geology in this area (Zone 4). You can see it’s a blue -grey colour, what we call the papa material that’s over 5.3 million years old.”

Work is well underway on a new bridge over the Manawatū River at the western end of the gorge.

Waka Kotahi

Work is well underway on a new bridge over the Manawatū River at the western end of the gorge.

Work was well under way on a new bridge over the Manawatū River at the western end of the gorge.

About 300-350 people were working on site each day and there were more than 150 pieces of machinery being used.

Workers were planning to plant two million trees and plants in the project area.

The road was designed so that cyclists and walkers would be able to safely travel the route on a shared path.

The project was aimed to completed by December 2024.

State Highway 3 through the Manawatū Gorge has been closed since severe weather in April 2017 caused slips that damaged the road.

Continued instability at the Kerry’s Wall site has closed the gorge indefinitely.

Traffic travelling between Tararua and Manawatū has been using the Pahiatua Track which traverses the northern end of the Tararua Range, or the Saddle Road which cuts across the southern end of the Ruahine Range.

Te Ahu a Turanga: Manawatū Tararua Highway route map between Woodville and Stoney Creek Rd

supplied

Te Ahu a Turanga: Manawatū Tararua Highway route map between Woodville and Stoney Creek Rd

The new highway is located to the south of The Saddle Road.